Changes to Board of Directors 

As a result of the open call for non-executive directors launched in May 2023, the board appointed the following two new members:  

  • New principal funding director: Paul Mumford, representing Urban&Civic. 
  • New stakeholder director: Kathryn Mackenzie, from the RevIvel Association and the Upper & Bedford Ouse Catchment Partnership. 

Both new directors joined an in-person board meeting on 10 October 2023 to agree the final Regional Water Resources Plan. 

New members 

The following organisations were approved by the board to become standard members of WRE: 

  • Kisters UK: An international environmental data and insights organisations specialising in water, weather, energy, environment and IR sectors.   
  • Seneye: A company that specialises in water monitoring systems for use in aquariums. Seneye are now looking at using their technology to branch into monitoring water quality in rivers. 
  • Stanley-Jones Consulting: A consultancy firm run by Hannah-Stanley Jones, the previous representative for Anglian Water on WRE’s Board. Has a background in strategic water resources planning from a water company perspective.  
  • Danino Consulting: A consultancy firm run by Vittoria Danino, specialising in water and the environment. Vittoria used to run the Anglian Centre for Water Studies at UEA and has experience in delivering projects, developing bids and co-designing and delivering workshops.  

Regional Plan approval 

The team presented the Regional Water Resources Plan for Eastern England to the board of directors and highlighted the main developments since the draft plan stage. Notable changes include a new chart showing demand management, a new map showing environmental improvements, a fuller cost-benefit section including the least cost pathway, and a section on adaptive planning which discusses decision points. The board approved the plan subject to final changes being made. 

Context for WRE’s next Business Plan 

The board discussed the following topics that will inform WRE’s revised Business Plan: 

  1. Defra’s Local Resource Options for agriculture fund and water resources planning for agriculture: Funding may be available from Defra to support the fund; updates on this will be reported back to allow WRE to have funding to co-ordinate and participate. Draft proposals will be worked up at a forthcoming workshop. 
  1. Taking forward Environmental Destination Studies including WINEP investigations: the EA has written draft guidelines which are yet to be finalised that set out how each region requires a regional environmental destination options appraisal package which will sit as an umbrella taking information from water companies and other sectors, looking at catchments and models.  
  1. Cambridge Water Scarcity Working Group: A Water Scarcity Working Group is being set up. The EA is beginning to object to individual planning applications on the basis of risk or deterioration to waterbodies which is leaving 9,000 homes on hold at the moment.  There will remain pressure on water supplies until new supply side schemes enter service in around 2032 and there are no additional schemes that can be brought forward to avoid this, with a priority being placed on demand management. Government is being brought in to discuss how to reduce water consumption so additional growth can be accommodated. WRE is requesting funding to model additional growth scenarios and the supply-side options required, however WRE is advocating that there should not be any weakening in environmental safeguards. 
  1. Fens and Lincs Reservoirs System Benefits: A study has been commissioned by Anglian Water to knit the two reservoirs with the current plans and potential use of the water within the systems to meet the needs of agriculture and deliver flood risk management benefits, supported by internal drainage boards and the Environment  the Environment Agency. A study is also being discussed to consider the impact on food production around the reservoirs and how the loss of productive land can be mitigated. 

Update on Regional Water Resources Funding and Governance Studies:  

A letter from Defra and the EA received in January 2023 confirmed there will be a second round of regional planning. This also flagged the need to ensure regional groups are adequately resourced and have appropriate governance. Mott MacDonald is considering governance of regional planning and a report from Arup in the spring will make recommendations on funding the regional groups. The EA has asked for bids for short-term, multi-sector funding for regional groups. WRE’s proposals include replacing membership fees from non-PWS board members, money for WINEP investigations on a multi-sector basis, money for catchment water resource planning tools, and money to support catchment management oversight and local nature recovery strategies across the region.  

The Mott MacDonald draft report was discussed. This gives added emphasis to the role of catchment partnerships and abstractor groups which could result in new multi-sector, sub-regional groups being formed to feed into regional plans.  

Revised WRE Business Plan for 2024 to 2028 

Feedback from WRE members on the draft business plan was discussed with proposals for how to address the points raised.  In response the board agreed to:  

  • Create measures of success even if these need to be measured on a qualitative basis where necessary at this stage. 
  • Commit to developing further quantitative measures. 
  • Explain this in the introductory text. 
  • Transition to a merits-based board appointment approach overseen by the Nominations and Remuneration Committee, as and when a new source of funding is secured to replace fees from principal funding members.  

WRE’s revised Business Plan for the 2024-2028 period was approved for publication by the board of directors, with the aim to launch this at the AGM in December 2023.  

Cambridge Water Scarcity Working Group 

Main announcements following the Autumn Statement are as follows: 

  • The government will support the Cambridge Delivery Group to drive the long-term vision for Cambridge by exploring the case for a development corporation.  
  • A further £2 million will be available to address water scarcity in Cambridge, alongside £3 million to support the Cambridge Delivery Group drive the long-term vision for Cambridge. 
  • It also confirmed £110 million for the Local Nutrient Mitigation Fund and will support local planning authorities affected by nutrient neutrality rules to deliver high quality local nutrient offsetting schemes, unlocking up to 40,000 homes over the next five years. 

However, further details are still awaited on:  

  • Policy reforms: including a possible water efficiency credits system, tighter building regulations, and allowing communal non-potable water supplies to new homes. 
  • Funding for WRE: modelling of higher growth scenarios for Greater Cambridge.  
  • Agri water resources planning: piloting approaches to catchment supply-demand assessments and local resource options.  
  • Nature-based solutions: trials to validate NbS groundwater models in the Cam and potential startup funding for rollout. 

WRE’s Annual General Meeting 

The AGM will be held on Thursday 14th December at 1pm. Notices will be sent to all WRE members around a month in advance.  This will be followed by a webinar that will launch WRE final Regional Plan. The board discussed and approved the Annual Directors’ Report to the AGM, including a new section on propriety and regularity. 

Changes to team 

Rebecca Bishop will be moving on from WRE to continue her travels that were cut short due to the Covid-19 pandemic. Alice Leonard will be starting at the beginning of January 2024 to replace Rebecca and Hannah Gray will be taking over as the new Norfolk NbS Programme Lead, also in January.